    Content:

    Hi Gurus,

    In Core manage application, in the date area how do we view for a month. As now now there are only for days and weeks.

    At times I could see the day/week duration or I could see scheduled or non scheduled, How do we change between these two?

    Thanks,

    Madhu 

    Image:

    Answer

     

    • Zsolt

      Hi Madhu,

      In the recent OFSC there is only one place where you can see activities for multiple days: Time View. All other views can show activities just for a specific day (except non-scheduled ones which isn't has execution day specified). The "scheduled" and "non-scheduled" option only available for List View.

      In OFSC 18C we will have a month view over the current "Day - 2 days - 3 days - 1 Week". The new structure is "Day - 2 days - 3 days - Week - Month", but still just for the Time View.

      FYI http://communities.rightnow.com/posts/3a17df3141

      Regards,
      Zsolt